For one of the largest manufacturers of nutritional supplements for animal feed worldwide, who is using AZ plug valves, we conducted a speed repair.
Like every 5 years, the ammonia line had to be serviced, as did the first half of the valves involved: a total of 23 valves and 21 actuators. The catch: the repair had to be completed in under 10 days, including pickup and delivery. Thanks to the active commitment of our international team, lead by Benjamin Selosse, the repaired valves were back in the factory three days before the deadline.
The customer is impressed with our work and was able to complete the maintenance on time. The maintenance and repair of the second half of the valves follows in October. No problem with AZ!